TANKER TECHNOLOGY tion crew is 40. The extra capacity is to house temporary crew during planned maintenance activities.
Processing Systems
The topside processing system consists of three major plants: the crude oil processing plant; the water injection plant; and the gas lift compression plant (future option). The crude oil processing plant separates well effluent in dry crude, gas and water. The dry crude is stored in tanks.
The available gas is used in the power plant as fuel gas, lift gas, pilot and purge gas, and the bal- ance is flared in a flare stack. The produced water is cleaned prior to discharge overboard.
Water injection facilities consist of filtration de-aeration, chemical injection and HP water injection pumps.
As an option, gas lift facilities can be installed aboard Glas Dowr.
The gas lift facilities will consist of
Like a bridge over troubled waters,, we will ease your mind.
With Cegelec's Electrical Propulsion Systems :ome 60 years of experience and innovation . It comes as standard. We have a global customer base, and Reassurance. .
For over half a century, Cegelec have been innovators in on-board power generation, electrical propulsion and control systems for the benefit of our customers. Innovations that have led to increased reliability, lower costs and improved safety.
But it's our focus on customers and quality, our commitment to develop the most cost-effective solutions, that has enabled us to win and to retain long term partnerships.
C E G E
Cegelec Projects Ltd., Boughton Road, Rugby, CV21 1 BU, UK
Tel. +44 (0)1788 563303 Fax+44 (0)1 788 563759 Telex 311335 http://www.cegelecproj.co.uk
W l , the capabilities to service it. And we're a single source supplier, with all the accompanying benefits of shorter lead times, greater coordination, and, of course, both commercial and technical accountability.
Want to be part of an innovative future....? Call us now.
Cegelec is the systems integrator and general contractor in the Alcatel
Alsthom Group.
Cegelec-lndustrial Equipment Division, 3 avenue des Trois-Chenes, 90018 Belfort Cedex, France
Tel.+33 (0)3 84 55 30 30 Fax. +33 (0)3 84 55 20 65 a treatment plant, compressors, knock-out drums and gas coolers, to recycle lift gas between the
FPSO and the reservoirs.
All processing and injection equipment is served by chemical injection skid injecting chemicals to various locations.
Circle 227 on Reader Service Card
Glas Dowr Data
Storage Capacities:
Exportable crude storage (dry crude @ 98%) 104,437 cu. m. (657,000 bbls)
Slop tanks (produced water) 6,652 cu. m. (41,838 bbls)
HFO storage 2,655 cu. m. 00 storage 1,764 cu. m.
Handling Capacity
Intake:
Max. fluid intake 75,000 bpd
Min. fluid intake 3,000 bpd
Offloading:
Offloading rate (max.) .3,975 cu. m./hr. (25,000 bbls/hr.)
Max. discharge pressure at pump 15.7 bar
Max. water content in export crude 5%
Note: The offloading system can handle shuttle tankers up to 150,000 dwt.
Process Plant:
Fluid capacity 3,000 to 75,000 bpd
Max. crude production 60,000 bpd
RVP 10.0 psia
H2S 0 ppm
Note: The range of the inlet pressure at the ESD valve upstream of the process plant is 150 to 300 psi. The range of the inlet temperature at the ESD valve upstream of the process plant is 85 to 99 degrees F (start-up, minimum 7 degrees)
Water Injection
Max. capacity 100,000 bwpd
Injection wellhead pressure 3,800 psia
Oxygen content lOppbmax.
Filtration quality95 percent removal of all particles greater than 5 microns
Max. injedion temp. .1 to 5 degrees above actual seawater temp. 40 Maritime Reporter/Engineering News