Page 33: of Maritime Reporter Magazine (July 2010)
Satellite Communication Edition
Read this page in Pdf, Flash or Html5 edition of July 2010 Maritime Reporter Magazine
July 2010 www.marinelink.com 33
On June 24, the first foundation was installed at sea for the Sheringham Shoal offshore wind project. Con- struction work on land is already well underway, and the 88-turbine wind farm is scheduled to start operation in 2011. The first of 90 monopile foundations was installed off the Norfolk coast by the heavy lift vessel “Svanen”.
Over the next nine months, the vessel will install the re- maining 89 foundations ready for the mounting of two substations and 88 wind turbines. “On land, we’re already well ahead, the substation is nearing its final form, and the onshore cable is nearly finished. Now that offshore installation is getting un- derway, this is a big day for us,” said Project manager in
Statoil, Elly Kristine Bjerknes
Substantial dimensions
A monopile foundation consists of a tubular steel monopile, driven 32-36 m into the seabed, and weighing from 400 to 600 tons. A transition piece is fitted to the top, forming the support for the turbine tower itself.
Each piece is 22m high and weighs about 200 tons. In- stallation of a submarine export cable is scheduled to begin in August, and submarine infield cables that con- nect the turbines and substations together in an intricate matrix on the seabed will start in October.
The first of 90 monopile foundations was installed off the Norfolk coast by the heavy lift vessel “Svanen”. “Sheringham Shoal is a pioneering project for Statoil, since it’s our first wind farm,” says Bjerknes. “We are a small but effective team working on this, and we have had excellent help and support from other sectors of the organization. We really feel that we’re crossing energy frontiers,” she says.
Rapid progress
Project Director Rune Rønvik says that this is a major milestone marking the culmination of many years’ plan- ning. “The license for the wind farm site was granted in 2004 and so it’s a great achievement to now be at the stage where we are starting a continuous process to in- stall the 90 required foundations,” he said. The Sher- ingham Shoal Offshore Wind Farm is owned equally by
Statoil and Statkraft through the joint venture company
Scira Offshore Energy Limited. Statoil is the operator for the project during the development phase. Scira will be the operator of the wind farm.
Offshore Wind Project Report
Sheringham Shoal Goes Offshore
Facts about Sheringham Shoal • 315 MW of installed capacity • Located off the coast of Norfolk, England • Covers an area of approximately 35 sq. km • 88 wind turbines, each with a 3.6 MW capacity • Turbine blade length 52 m (170 ft.) • Turbine tower height 80 m (262 ft.) • Wind turbines are placed on foundations on the seabed • Two offshore substations • Two 132 kV marine cables to come ashore at
Weybourne • 21.6 km underground cable will connect the wind farm to the National grid at a new substation (Source: Statoil)
The first foundation for the 317MW Sheringham
Shoal Offshore Wind Farm has now been in- stalled on the wind farm site. The monopile was installed by the twin-hulled heavy lift vessel Sva- nen, which has been used for similar operations at other offshore wind farms. (Photo Cr edit: Statoil)