Project/ Operator Topsides Jacket Notes Reserves

Current North Sea major projects shelf

With help from Infeld Systems, charts the current, ongoing major projects in the market place in Northwest Europe, covering the UK OE

Continental Shelf, ofshore Norway, Denmark and the Netherlands.

UK Continental Shelf (continued)

Captain Chevron New bridge-linked platform to house EOR process 360 MMboe

Project/ Operator Topsides Jacket Notes Reserves equipment for the Captain heavy oil feld. shelf

Cheviot Alpha FPSO redevelopment of the Emerald feld. Xodus First oil planned for 2020 Remaining recoverable

UK Continental Shelf

Blocks Petroleum Group awarded pre-FEED study this year with feld reserves of at least 55

Cygnus GDF Suez Four platforms, three bridge-linked: accommoda- Four jackets and 2014-2015 installation Gross proven and 2/10a, development plan and environmental statement to MMbo and 100 bcf

Blocks E&P tion platform, built at Burntisland Fabrication piles (total weight campaign by Seaway probable reserves of 18 2/15a and be submitted 2H 2015.

Northwest Europe 44/11A and (BiFab), Scotland, wellhead (2 x 1640-tonne) and 8000-tonne) being Heavy Lifting using the Bcm gas 3/11b. 44/12A 4000-tonne process and utilities platforms and produced by BiFab at its . The APU

Oleg Strashnov

FPF-1

Greater Ithaca foating production facility is being upgraded Sailaway scheduled for 1Q, Proven and probable a compression module, being built at Heerema Methil, Burntisland and topsides will be heaviest

Stella Area Energy at Remontowa’s yard in Poland. 2016, with frst production reserves of about 32

Fabrication Group (HFG), Hartlepool, compression Arnish yards. lift has

Oleg Strashnov block 30/6a 2Q 2016. MMbbl platform with bridges and other structures, HFG, ever performed. The

Hartlepool. Due March 2014-2015. Hartlepool deliv- Ensco 80 drilling rig in use

Rosebank Chevron 292m-long, 99,750-tonne FPSO, initially due to be Infeld estimates 240 ered the ACM, PU and Bravo Cygnus decks July. throughout.

205/1 built by Hyundai Heavy Industries (HHI). Project on MMbo and 400 Bcf hold to reassess economics.

Mariner Statoil Production, drilling and quarters platform with 50 21,000-tonne jacket: Production due to start 250 MMbbl recoverable 9/11a well slots, being built by Daewoo Shipbuilding and largest to be built by in 2017. Aker Solutions

In commissioning

Marine Engineering (DSME) South Korea, with Dragados Ofshore, contracted for engineering a foating storage unit alongside being built by Cadiz, Spain. Due to be during the hook up phase.

22,300-tonne and

Clair Ridge BP Drilling and production platform and quarters and Supported by Recoverable reserves of

Flotal

Samsung Heavy Industries (SHI). Drilling supported installed September 206/08 utility platform, fabricated by HHI, installed this . Due onstream 640 MMbo 9000-tonne jackets Victory by a jackup for the frst 4-5 years. Heavy lift opera- 2015. On 28 July, summer. mid-2017 built by Aker Solutions, tions is being carried out by Saipem while Subsea 7 Dragados loaded out

Norway, installed in 2013.

has the SURF contract. Odfell Drilling are carrying the large jackets for out the drilling services. See page 46. Mariner.

EnQuest

Alma/Galia EnQuest 7 production wells tied back to the Due onstream mid-20152P reserves of 34

Producer Uisge Gorm 30/24 and FPSO, previously Bluewater's , MMboe

Bressay Statoil Concept initially developed to mirror Mariner, but 100-300 MMbbl 30/25 capable of processing 57,000 boe/d and storing 3/28a it is being revised in 2015, with fnal investment recoverable 625,000 bbl crude oil. decision expected 2016. Statoil is still looking at a simplifed development concept compared with

Solan Premier 3500-tonne topsides built at Methil and Arnish 8000-tonne jacket, Due onstream 201530 MMbbl proven and earlier plans 205/26a Oil yards, Scotland, installed 2014. built at BiFab, Methil. probable oil reserves

Installed 2014.

Culzean Maersk 12 slot wellhead platform, central processing facility Ramboll Oil and Gas Targeted start up for 2019 Reserve estimates 22/25 Oil and utilities/living quarters. KBR contracted as awarded detailed design remain under wraps.

Norway topsides front-end engineering and design provider. for two jackets for the Although Maersk said

Wellhead access deck at HFG Hartlepool. MODEC central processing it could provide about Ivar Aasen Det 15,000-tonne platform, built by SMOE, a subsidiary 9000-tonne jacket built Recoverable reserves of and Teekay Ofshore competing for FSO contract. facility platform and a 5% of the UK's total PL 001B, Norske of Sembcorp, in Singapore and Batam, Indonesia, by Saipem at its Arbatax 210 MMboe

However, in May 2015, Maersk asked for revised separate utilities and gas consumption by 028B and due to be lifted into place in 1H 2016. facility in Sardinia and bids for the infrastructure of the feld. living quarter platform. 2020-2021 242 installed June 2015. 2100-tonne wellhead

Aasta Statoil Deck and living quarters for spar development, Spar hull, consortium of Start up due 2016. First Estimated 47 Bcf jacket to be built by HFG,

Hansteen HHI, South Korea. Living quarters subcontracted to HHI and Technip production spar on (recoverable) sailaway March 2016.

Hertel, Rotterdam. Norwegian Shelf.

Fyne Antrim Production buoy concept under consideration work- Proven plus probable

Martin Total 22,600-tonne topsides, SHI. Living quarters to be Jacket and piles weigh- FSO part of the project. Recoverable reserves of 21/28a Energy ing with Enegi Oil, license currently lapsed. reserves of 11.7 MMbbl

Linge (for- fabricated in Norway by Apply ing 21,400-tonne, Due onstream 2016. 190 MMboe

Montrose Talisman 9500-ton topsides, HFG, Zwinjdrecht, Netherlands. 5400-tonne jacket built Proven and probable re- merly Hilde) Kvaerner, installed 2014.

Arbroath Sinopec Due out March 2016. by OGN, Newcastle. serves estimated at 38

Gina Krog Statoil Topsides to be built by DSME, South Korea. Living 17,000-tonne launch Due onstream 2017Estimated 225 MMboe

Energy Sailed out 2014 MMboe plus 58 MMboe

Redevelop- quarters to be built at Stord, module in Poland. jacket, HFG Vlissingem, ment 22/17 UK of possible resources

Netherlands. Installed

Lancaster Hurricane See page 58 for a detailed feature on Lancaster. June

Darwin Taqa Up to 21 subsea wells tied-back to either a fxed Southern end of the former 29.6 MMboe Edvard Lundin 21,000 tonne topsides, Kvaerner. 13,400-tonne jacket, Due onstream 4Q 2015 Proven and probable block Bratani platform host facility or FPSO. Feasibility studies North West Hutton feld. Grieg Kvaerner Verdal, in- reserves of 186 MMboe 211/27a are ongoing. First oil anticipated in 2020 stalled 2014

Perth Parkmead See page 42 for a feature on the Perth hub

FPSOs 15/21C concept.

Vette Premier Sevan-type FPSO to be owned and operated by First production due in Probable reserves of 54

Bentley Xcite MOU signed with Teekay for a bridge-linked Sevan 250 MMbbl proven and (Bream) Oil Teekay Petrojarl on lease. 2019 MMboe

Block 9/3b Energy design foating storage and ofoading facility to be probable reserves linked to a self-installing ACE MOPU platform, with

In commissioning a newbuild N-Class drilling rig alongside.

Goliat Eni Sevan-type FPSO built by HHI in Ulsan, South Korea. Due onstream 2015Recoverable reserves of 178 MMboe

FPSOs

Catcher Premier FPSO to be supplied by BW Ofshore. Hull being built First oil due 2017 96 MMboe

Denmark 28/9a and Oil by IHI Corporation of Japan.

Hejre DONG Topsides, Technip/DSME consortium, South Korea, HFG jacket 8000-tonne Had been due onstream Recoverable reserves 28/10c

Energy pre-drilling wellhead deck, HFG, Netherlands delivered last year. in 2015, now scheduled estimated at about 170

Kraken EnQuest Bumi Armada will supply and operate the FPSO (an First oil due 2017 140 MMbbl gross oil for 2017 due to topsides MMboe

Blocks 9/2b ice-class tanker conversion to 600,000 bbl capac- reserves delays.

and 9/2c ity) for the heavy oil project.

Netherlands

Glen

Glen Lyon BP The Quad 204/Schiehallion redevelopment. First oil due 2017 Estimated recoverable

Lyon 204/20a FPSO being built by HHI in South Korea. Due to oil reserves of 450 P11-E ONE HFG is building an unmanned 500-tonne topside Sailaway due April 2016 be installed in 2016. See page 87 MMboe and 1000-tonne jacket powered by solar and wind .

Dutch Supplement energy. See page DO-12 of the .

Western Dana Sevan-type FPSO being built under contract with Behind schedule, due on Recoverable reserves

Isles Petroleum China's COSCO. stream 2H 2017 of approximately more A18 Chevron 950-tonne topsides and 1200-tonne jacket. Infeld estimates 170

See 210/24a than 45 MMbbl Bcf

Dutch supplement.

September 2015 | OE oedigital.com 84 084_0915_geofocus2_chart.indd 84 8/19/15 10:08 PM