Stevens Fishery

  • July brought news about offshore wind. There was something for everyone: optimism, disappointment, and construction, too.

    Finally, starting with Dominion Energy’s Coastal Virginia Offshore Wind Project, a joint venture with Danish wind developer Orsted is underway. True, this is a small project – just two wind turbines to be installed 27 miles east of Virginia Beach. But considering all the preceding hurdles, news about Dominion blew in as proverbial, hopeful fresh air. Surely, additional offshore wind construction news would quickly follow; news about a full line-up of projects ready to bust through interminable studies and studies of studies.

    Indeed, there is a lot of offshore wind energy in the developmental pipeline. The table below shows wind energy areas (WEAs) from the Bureau of Ocean Energy Management (BOEM) website, part of the Department of Interior.  BOEM leads all federal offshore energy siting and development in the Outer Continental Shelf (OCS), including wind.

    Offshore Wind: harder to install than an oil platform
    Importantly, a lease doesn’t mean there is a project is ready to go. In reality, there aren’t many projects advancing within most of the WEAs. There are a lot of project ideas. New York State, for example, on July 18, announced its selection of two ocean-based wind proposals, a selection in response to a high-profile solicitation last November. The projects, Empire Wind and Sunrise Wind, are planned for Atlantic Ocean WEAs OCS-A 512 and OCS-A 487, respectively.

    Except for Block Island in Rhode Island, all the work on US offshore wind is still preliminary, really just a library. Actually, the studies themselves are the projects. This investigative work is quite advanced in one or two WEAs. In others, lease holders have requested extensions. In some cases, work has stopped.

    Importantly, the Atlantic isn’t the only site with emerging projects.  Icebreaker Wind is a six turbine, 20.7-megawatt offshore demonstration project in Lake Erie, eight miles from downtown Cleveland.  It will be the first freshwater project in North America. It is winding down its regulatory and permitting requirements, awaiting final okay from the Ohio Power Siting Board. Construction is slated for 2022.

    The project most likely to start after Dominion is Vineyard Wind, off Massachusetts, about 14 miles from the southeast corner of Martha’s Vineyard.  Where power is concerned, this is the real deal: 800 MW, up to 100 offshore wind turbine generators.

    A check on the federal Permitting Dashboard shows that Vineyard is tantalizingly close to completing seven major federal studies required to move to construction.  Vineyard’s work is estimated to be complete by November 14, 2019. (See Table 2 for a list of the federal studies required from Vineyard.)

    Table 2: Federal Studies Required to Complete Vineyard’s Federal Environmental Review & Permitting Process:

    Study

    Agency

    Construction and Operations Plan

    Department of Interior (DOI) and BOEM

    Endangered Species Act (ESA) Consultation

    DOI – Fish & Wildlife Service (FWS)

    Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

    US Army Corps of Engineers

    ESA Consultation

    Department of Commerce (DOC), and NOAA

    Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation

    DOC and NOAA

    Incidental Take Authorization – DOC - NOAA/NMFS (National Marine Fisheries Service)

    DOC, NOAA, NMFS

    Environmental Impact Statement (EIS)

    DOI, BOEM

    (*) This Table is just an example. Some projects require additional federal studies.


    Shortly after Dominion’s optimistic announcement, Vineyard Wind received troubling news: that BOEM would not have its final approval – a Record of Decision – for the company’s Environmental Impact Statement, expected on July 5. BOEM said its review was not complete, that it needed to push its deadline to August, later than expected, but still within the Agency’s promised two-year window.

    On its website, Vineyard Wind presented a stoical reply, commenting that the delay was disappointing, but not surprising for a first-time project. Vineyard Wind needs the formal Record of Decision (ROD) by BOEM to set its construction team in motion. The logistics are daunting.

    There was more bad news for Vineyard Wind. This summary has only focused on federal reviews.  In fact, of course, there are state and local reviews. And in Edgartown, MA, on Martha’s Vineyard, the Edgartown Conservation Commission voted to deny Vineyard Wind the right to bury its transmission cables beneath Muskeget Channel, running through Nantucket Sound.

    This unexpected “no” vote sent some difficult messages. Among many state governors and legislators offshore wind is unquestioned as a social and economic boon. At the local level, support is fractured.  Vineyard Wind has since requested a superseding order from the Massachusetts Department of Environmental Protection (MA DEP) to overturn the Edgartown decision.  

    Residents in Easthampton, on Long Island, have raised similar, oppositional questions about the nearby South Fork project and its impact on Easthampton. Town officials may seek outside project review.  New York’s Department of Environmental Conservation has filed a preliminary nine-page set of comments advising NY’s Public Service Commission that additional, extensive analysis is required before the project should be considered for a Certificate of Environmental Compatibility and Public Need.

    In a message to BOEM, Vineyard Wind noted that “for a variety of reasons, it would be very challenging to move forward the Vineyard Wind 1 project in its current configuration if the final EIS is not issued within, approximately, the next four to six weeks” – or the end of August. MA DEP has up to 70 days to review Vineyard Wind’s request. A DEP spokesperson said the review will likely not take that long.

    For Vineyard Wind, events may still turn as the company needs, but will that be timely? A Record of Decision is not an ending; it allows the next step within a much bigger process and sequence. A ROD confirmed in September could mean staying on schedule for work planned for November. A confirmation in November might be too late, for many reasons: weather challenges, marine mammal restrictions and, critically, too late to confirm contracts with specialty equipment suppliers and vessel operators.

    All Logistics are Local
    After BOEM’s decision, next steps aren’t much easier. Construction requires specialized vessels and equipment.  Just how that might work is drawing a lot of brain power. The central challenge is that there are no American vessels available, as required by the Jones Act, for work in U.S. territory. It appears there are no vessels in the U.S. shipyard construction queue, either.

    There are vessels available on the world market, but the Jones Act makes it difficult – almost impossible, save a waiver – for non-U.S. vessels to work in the United States. The Jones Act requires that all vessels working in US waters are American owned, American built and American crewed.
    Emily Huggins Jones is an attorney with Squire Patton Boggs, based in Cleveland. She recently participated in a panel discussion, in Amsterdam, presented to European firms interested in the emerging US offshore wind market. Her advice: don’t expect a Jones Act waiver.

    Huggins Jones predicts that an initial project will follow the protocol used for Block Island: the requisite, foreign equipment will be moved to a work site, but not to a U.S. port. However, it will be supplied by Jones Act compliant vessels and barges.

    She said this deliberate distancing can work to get this new industry started. “Will it be the same in ten years?” she asks rhetorically. “Probably not,” she adds, “but we’ll likely be at a place where those issues have been worked out.” Huggins Jones said discussions are underway now at various corporate levels about whether it makes sense to have a pool of equipment, like the oil and gas industry. High costs are not the only problem. A bigger concern lurks in the background: whether there will be enough offshore wind work to justify those investments.

    Separately, Icebreaker Wind officials (Lake Erie) are also thinking about the Jones Act. Dave Karpinksi is Icebreaker’s VP of Operations. He was asked about plans for vessels and equipment. Ideas include bringing in a heavy lift vessel through the St. Lawrence Seaway or modifying an available barge with a heavy crane. “We haven’t committed to one plan yet,” Karpinski said, adding, “We’ll need approximately 1 to 1½ years lead time.” Karpinski said a foreign heavy lift vessel would be Jones Act compliant because “we wouldn’t be coming into any U.S. port. This is how the Block Island Wind Farm turbines were installed.”

    Separately, Orsted responded to questions about their marine strategy by saying in a prepared e-mail message, “While we won’t be using a Jones Act compliant vessel for the installation of the foundations and the turbines, because one does not exist, we will ensure that any construction activities are fully compliant with all relevant rules and regulations.”

    Looking Ahead: one size does not fit all
    On the world market, then, there is considerable doubt that the equipment available to take on the addition of concurrent U.S. offshore wind construction projects.

    Jurgen de Prez is Commercial Director of Jack-Up Barge (J-UB), a Netherlands based company that provides self-elevating platforms for the global offshore energy market. De Prez was asked about supply and demand. Right now, he said, there is some overcapacity in jack-ups. But he expects that to change when new U.S. and Asian projects start, placing new demands on existing equipment working in the North Sea. Another upcoming issue, de Prez explained, is that increases in turbine capacity require jack-ups with longer legs and larger cranes. “In this emerging market segment,” de Prez noted, “there will be an undersupply.”

    Equipment used by the oil and gas industry cannot install foundations and wind turbines.  Right now, J-UB’s contracts are set about two years in advance. De Prez estimated industry lead time averages between one and a half and two years.

    Offshore wind requires multiple specialized vessels. Each project is different, but De Prez said that, generally, a jack-up barge would be towed to the work site. Some jack-ups are outfitted with propulsion systems, allowing autonomous movement within the offshore windfarm. The exact vessel used depends on the phase of construction, de Prez explained. Foundations could be installed by a floating unit or a jack-up, but only a jack-up installs turbines. Cable lay vessels link it all together.

    In a way, actually building an offshore wind farm isn’t the hardest part. The hardest part, really multiple parts, is starting a new industry almost from zero. It takes a lot of energy to reach critical mass – before it’s all linked together.

    Only one thing is for certain today. When it comes to offshore wind – domestic offshore wind – getting these clean, green and renewable energy projects done is probably more difficult than getting permission to build a refinery. Opposition comes from many – sometimes surprising – quarters. The wind is coming; you can almost feel the breeze. The only question is: when?

    This article first appeared in the September 2019 print edition of MarineNews magazine.


  • MT Jan-24#25  into the vehicle.”
Ann Stevens, Vice President, 
Boeing)
    January 2024 - Marine Technology Reporter page: 25

    “The sky’s the limit in terms of payloads that can be brought into the vehicle.” Ann Stevens, Vice President, Boeing Maritime & Intelligence Systems subsea vehicles, speci? cally vehicles with increased endurance nautical miles. “You can go for months at a time without requir- to allow them to be deployed

  • MT Jan-24#24  a payload section, said Ann Stevens, 
VP, Boeing Maritime)
    January 2024 - Marine Technology Reporter page: 24

    to the U.S. Navy over the next 18 months. The ? rst unit is to be used as a test asset for the Navy, so it doesn’t have a payload section, said Ann Stevens, VP, Boeing Maritime and Intelligence Systems. The XLUUV, designated by the Navy as “Orca,” is a new class of autonomous sub- marine designed for

  • MT Jan-24#12 INSIGHTS  AERIAL DRONES & MINE HUNTING
UNMANNED AERIAL)
    January 2024 - Marine Technology Reporter page: 12

    INSIGHTS AERIAL DRONES & MINE HUNTING UNMANNED AERIAL SYSTEM HAS EARNED ITS SEA-LEGS By Edward Lundquist he Swiss-Swedish joint-venture UMS Skeldar V-200 mum take-off weight of 235kg, a maximum speed of 75 knots vertical take-off unmanned arial system (VTUAV) and a payload of up to 40kg. It can take

  • MT Jan-24#4  into the vehicle” is how Ann Stevens, 
Production Manager
)
    January 2024 - Marine Technology Reporter page: 4

    that can be loaded into its considerable payload bay. In fact, “The sky’s the limit in terms of payloads that can be brought into the vehicle” is how Ann Stevens, Production Manager Irina Vasilets Vice President, Boeing Maritime & Intelligence Systems, said it in our recent interview vasilets@marinelink

  • MT Jan-24#2   Interview: Ann Stevens, Boeing 
Maritime & Intelligen)
    January 2024 - Marine Technology Reporter page: 2

    Authors & Contributors 7 Editorial Board 18 Tech Feature: Wave Power 42 22 Interview: Duane Fotheringham HII Mission Technoloiges 24 Interview: Ann Stevens, Boeing Maritime & Intelligence Syst. 48 Pro? le: NBOSI 50 Tech Feature: Battery Thermal Management 54 Tech Feature: Floating Offshore

  • MT Sep-23#57 heat transfer material behind the PCB  letters are bare)
    September 2023 - Marine Technology Reporter page: 57

    heat transfer material behind the PCB letters are bare aluminum. components, and do lots of testing pre- to carry the heat away from the LEDs deployment. Cree LEDs produce more (google “CREE LED Luminaire Design Many parts can be purchased by an light per watt, so less heat, and their Guide”). LEDs

  • MN Oct-23#25 the science here, its use, codes and 
protocols to ensure)
    October 2023 - Marine News page: 25

    the science here, its use, codes and protocols to ensure safety.” Getting the permits In a section referencing “Proposed Future Work,” still for 2023, project managers will seek to ? nalize design and development and pursue permitting “from authorities having jurisdiction.” In the 2023 AMR a section

  • MR Sep-23#51 , U.S. Coast Guard Academy, Stevens 
a series of incidents)
    September 2023 - Maritime Reporter and Engineering News page: 51

    colleges include SUNY, U.S. Mer- safety of offshore infrastructure in the North Sea following chant Marine Academy, U.S. Coast Guard Academy, Stevens a series of incidents that raised fears of attacks on underwa- Institute, Webb Institute, Rutgers University, Old Dominion ter internet cables,

  • MR Sep-23#30 NATIONAL SECURITY MULTI-MISSION VESSEL (NSMV)
NSMV POWER)
    September 2023 - Maritime Reporter and Engineering News page: 30

    NATIONAL SECURITY MULTI-MISSION VESSEL (NSMV) NSMV POWER PLAY The quest to build a series of five National Security Multi-Mission Vessels (NSMVs), which will serve as training ships for five U.S. maritime academies, has drawn a broad cadre of suppliers. The powerplant was a main focus, helping to evolve

  • MN Aug-23#30  million modernization pro-
Stevens Towing recently added)
    August 2023 - Marine News page: 30

    Systems held a groundbreaking ceremony Marinette, Wis. Shipyard Fincantieri Marinette Marine, of? cially kicking off a $200 million modernization pro- Stevens Towing recently added an 820-metric-ton-capacity Marine Travelift 820CII mobile boat hoist to join its 150-ton hoist already on site at its shipyard

  • MN Aug-23#29  and govern- In addition, the Stevens Towing Shipyard facility)
    August 2023 - Marine News page: 29

    Southern California-based Marine Group Boat Works, dry dock time frame for them.” which performs a mix of yacht, commercial and govern- In addition, the Stevens Towing Shipyard facility will ment vessel repair work, in 2022 repowered its 665-ton now be equipped to haul out 60-foot-wide barges, making Marine

  • MR Apr-23#24 INTERVIEW KEVIN SLIGH SR., DIRECTOR, BSEE
Report] and FIR)
    April 2023 - Maritime Reporter and Engineering News page: 24

    INTERVIEW KEVIN SLIGH SR., DIRECTOR, BSEE Report] and FIR [Fabrication and Installation Report] re- need to have consensus-based safety standards that will then views are being coordinated between BSEE and BOEM. be incorporated by reference back into our new 285 Reg that We’ve brought on the Army Corps

  • MR Aug-22#32 , Jack H. Lucas (DDG 125), Ted Stevens (DDG 128), Jer- • USNS)
    August 2022 - Maritime Reporter and Engineering News page: 32

    at Ingalls, including Lenah Sutcliffe Higbee (DDG • USNS Lucy Stone (T-AO 209) – under contract 123), Jack H. Lucas (DDG 125), Ted Stevens (DDG 128), Jer- • USNS Sojourner Truth (T-AO 210) – under contract emiah Denton (DDG 129) and George M. Neal (DDG 131).” • John L. Canley (ESB 6)

  • MT Jul-22#55 Bioch L L L L Left: hemist 
D Dr. Sarah S Seabrook. .)
    July 2022 - Marine Technology Reporter page: 55

    Bioch L L L L Left: hemist D Dr. Sarah S Seabrook. . Voya Ri R R R ght: age l leader and d marine g geologist K Kevin M Mackay. Photo credit: NIWA-Nippon Foundation TESMaP / Rebekah Parsons-King Photo credit: NIWA-Nippon Foundation TESMaP / Rebekah Parsons-King see it from space. be a while before it is

  • MR Jun-22#45 UNITED STATES COAST GUARD
Deputy Sector Commander for)
    June 2022 - Maritime Reporter and Engineering News page: 45

    UNITED STATES COAST GUARD Deputy Sector Commander for Sector Honolulu Cmdr. Aja Kirksey said the option of sending an FRC with a WLB to- gether as a surface action unit (SAG) has proven to be success- Sentinel Class Fast ful. But these long deployments have risk, and we shouldn’t assume that because

  • MR Jun-22#44 UNITED STATES COAST GUARD
U.S. Coast Guard photo by Petty)
    June 2022 - Maritime Reporter and Engineering News page: 44

    UNITED STATES COAST GUARD U.S. Coast Guard photo by Petty Of? cer 3rd Class Scott Sabatini/Released A boat crew from the USCGC Joseph Gerczak (WPC 1126) transports NOAA Fisheries and American Samoa Marine Police members to conduct ? sheries law enforcement in the American Samoa exclusive economic zone

  • MR Jun-22#43 UNITED STATES COAST GUARD
“Our 50 gallons-per-hour fuel)
    June 2022 - Maritime Reporter and Engineering News page: 43

    UNITED STATES COAST GUARD “Our 50 gallons-per-hour fuel consumption only works if The Coast Guard Cutters Joseph Gerczak we have both main engines running optimally at 900 rpm. We and Juniper refuel in Papeete, Tahiti, can’t maintain speed and be fuel ef? cient on a single engine. while underway

  • MN Jun-22#42 People &
Companies
Waterjet propulsion systems suppli-
Fagan)
    June 2022 - Marine News page: 42

    People & Companies Waterjet propulsion systems suppli- Fagan Con? rmed as er Marine Jet Power announced it has USCG Commandant appointed Kevin Kirby as president of Adm. Linda L. Fagan has been con- ? rmed as the 27th Commandant of MJP, Inc. and regional sales director of Fagan Schultz the U.S.

  • MT May-22#21 By Kevin Hardy, Global Ocean Design LLC, MTR columnist
here)
    May 2022 - Marine Technology Reporter page: 21

    By Kevin Hardy, Global Ocean Design LLC, MTR columnist here is a palatable excitement when an ocean lander is buoyancy budget is the use of a material selected for its speci? c released to explore the deep sea. The checklists and end- gravity, strength and bulk modulus. All things being equal, se- less

  • MN Mar-22#43 People &
Companies
Fuentes who will serve dual roles as)
    March 2022 - Marine News page: 43

    People & Companies Fuentes who will serve dual roles as sec- Vekich Swon in as FMC retary and treasurer. Each will hold their Commissioner positions for a two-year term. Max Vekich was sworn-in as a Com- Vekich Kastner missioner of the Federal Maritime Com- New Leaders at MITAGS mission for a term

  • MT Sep-20#49 UC San Diego students Mi-
chelle Sit, Raymond Young)
    September 2020 - Marine Technology Reporter page: 49

    UC San Diego students Mi- chelle Sit, Raymond Young, Hunter Woodruff, and Jacob Springman collaborate via Zoom on their team project, which is sponsored by Boe- ing. The group is developing a software suite of autonomous unmanned surface vehicle be- haviors that could help scien- tists monitor the

  • MT Jan-22#54 Tech File
Innovative new products, technologies and)
    January 2022 - Marine Technology Reporter page: 54

    Tech File Innovative new products, technologies and concepts JW Fishers Helps to Locate Missing Persons In 2020, Berkshire County purchased a JW Fishers Side Scan Sonar system. In May 2021 the Berkshire County Sheriff’s Of? ce was called to assist local and state authori- ties in searching for a man

  • MR Dec-21#36 TECH FEATURE NAVIGATION RADAR
GINA helps guide 
Sikuliaq)
    December 2021 - Maritime Reporter and Engineering News page: 36

    TECH FEATURE NAVIGATION RADAR GINA helps guide Sikuliaq through the ice he research vessel Sikuliaq, a Center notes that satellites have only Oceanic and Atmospheric Administra- 261-ft. ice-capable research ves- been continuously monitoring sea ice tion’s Joint Polar Satellite System. sel operated by UAF

  • MT Nov-21#42 DESIGN  UNDERWATER NOISE MITIGATION
LESSONS LEARNED IN)
    November 2021 - Marine Technology Reporter page: 42

    DESIGN UNDERWATER NOISE MITIGATION LESSONS LEARNED IN SETTING UNDERWATER RADIATED NOISE TARGETS: A BC FERRIES CASE STUDY By Greg Peterson BC Ferries, Director of Engineering, Chanwoo Bae, BC Ferries, Engineering Manager (Naval Architecture), and Derek White, Vancouver Fraser Port Authority, ECHO