The Standard Oil Co. (Ohio) reported that the company will have spent $140 million by the end of this month as its share of engineering, research, design and equipment costs on the Trans-Alaska Pipeline.

"Sohio's share of the Alaskan pipeline expenditures this year might amount to $200 million to $250 million if construction starts as scheduled this spring since the right-of-way permit, applied for in June 1969, was issued January 23," said Charles E. Spahr, Sohio board chairman.

Total capital expenditures by Sohio are expected to be in the range of $2 billion to $2.5 billion over the next five years, primarily for the development of Alaskan oil and gas reserves and construction of the Trans-Alaska Pipeline.

In addition to the expenditures in Alaska, Sohio expects to spend about $200 million for completing an expansion and modernization of a refinery in Marcus Hook, Pa., and conversion of Sohio's Toledo, Ohio refinery to processing high sulfur crude oil. The Marcus Hook program will be completed late this year, and the Toledo project in late 1975.

Sohio plans to enter into longterm charters of tankers over the next few years to transport foreign oil for use in its refineries and to move Alaskan oil to the 'West Coast. The cost of these tankers to their owners will be in the area of $500 million to $750 million.

Mr. Spahr said the $140 million spent thus far on T A P S is the first part of Sohio's share of the estimated $4-

Maritime Reporter Magazine, page 17,  Mar 1974

Read Long-Term Charters Planned By Sohio in Pdf, Flash or Html5 edition of March 1974 Maritime Reporter

Other stories from March 1974 issue

Content

Maritime Reporter

First published in 1881 Maritime Reporter is the world's largest audited circulation publication serving the global maritime industry.