Emergency Sends S.S. Matsonia to Pearl Harbor Yard

A propulsion casualty aboard the 760-ft. (231.6-m) SS Matsonia in June created a unique opportunity for the private sector and the Navy to work together and maintain a vital supply line to Hawaii — a cooperative effort between Pearl Harbor Navy Shipyard and Honolulu Shipyard, Inc.

The Matson flagship vessel, which experienced an intermediate shaft failure 700 miles off Oahu, was brought to the Navy's 1,100-ft.

(335.2-m) dry dock — the largest of four - for emergency repairs on June 23, 2003. It is the largest ship to be dry-docked at Pearl Harbor Naval Shipyard since the USS Yorktown in May 1942.

Bill Clifford, president and CEO of Honolulu Shipyard also noted that the cooperation and teamwork demonstrated between agencies (government, military and private) is unprecedented tor this type of emergency repair effort.

U.S. Rep. Neil Abercrombie. (D-Hawaii). is working on a pilot program at Pearl Harbor that would bring one of the 11 maritime pre-position ships that act as forward- based stocks of U.S. military equipment in the Pacific. The ships bypass Hawaii, pass through the Panama Canal, offload equipment in Florida, and head up the East Coast for repairs that keep them out of operation for four months — twice as long as they would be if they dry docked in Hawaii.

Circle 58 on Reader Service Card

Maritime Reporter Magazine, page 30,  Aug 2003

Read Emergency Sends S.S. Matsonia to Pearl Harbor Yard in Pdf, Flash or Html5 edition of August 2003 Maritime Reporter

Other stories from August 2003 issue

Content

Maritime Reporter

First published in 1881 Maritime Reporter is the world's largest audited circulation publication serving the global maritime industry.