Productivity Advances In Shipbuilding
The Desire To Reduce Shipyard Production Manhours Leads Avondale To Production-Line Ship Construction During World War II, ships were built in the United States at a rate which may well have been the most productive in terms of ships per day being produced that has ever been accomplished. A major reason for that productivity was that many ships of the same type were constructed one after another in a given shipyard. This allowed utilization of special tooling and allowed personnel to become proficient in accomplishing the same task over and over again. In many ways, production-line techniques could be, and were, utilized in the construction. Another significant advantage was the ability to make large quantity procurements of equipment and materials. After World War II, the shipbuilding practices which had been common prior to the war became common again.
During the ensuing 20 years, shipyards in other countries, such as Japan and in Europe, were developed or modernized using upto- date production engineering principles. By the early 1970s it was clear that most shipbuilding in the world was being accomplished outside the United States.
At that time, the Maritime Administration conducted several investigations of worldwide shipbuilding practices and provided seed money for shipyards to attempt to improve their own capability for decreasing shipbuilding costs. Many shipyards also made independent efforts to investigate foreign shipyards and to investigate new shipbuilding techniques.
One of the most notable efforts was the then new shipyard at Pascagoula, Miss., established by Litton/ Ingalls. It was based largely around automated machinery, a good flow of materials into the areas where fabrication took place, and a concept of building ships in large sections which were outfitted as they were being built. These sections were then welded together and launched, using a launch platform. These were very innovative steps which were well suited to building runs of several ships.
For another example, Avondale Shipyards (ASI) sent a team of engineers to Japan and to Europe as early as 1972 to investigate the techniques used by Japanese and European shipbuilders. Somewhere in that time frame, as the world demand for ships decreased, some of the Japanese companies decided that it was to their advantage to begin to export the technology which they had been using to build ships so effectively. The combination of these several efforts resulted, at Avondale, in a commitment by Avondale management to have a Japanese company, Ishikawajima-Harima Heavy Industries Co. (IHI), make an indepth study of the way Avondale was building ships and make recommendations to Avondale for things which could be done to improve productivity.
Consequently, a contract was signed in 1974 which resulted in five Japanese engineers being assigned by IHI to Avondale Shipyards.
These men have been participating directly with Avondale employees in the planning and construction of a new class of product carriers which Avondale had contracted to build for Exxon.
The approach recommended by IHI required major changes to the existing sequence of construction and resulted in major changes to the type and timing of the design effort.
Recognizing the potential advantage to Exxon, as well as to Avondale, of the new techniques Avondale was trying to use, Exxon participated fully with Avondale in studies of the details of the ship design and with modifications to the ship design. This degree of involvement between the owner and the shipbuilder at this stage of the design process was unprecedented in ASI's commercial experience.
The result was a period of about six months prior to the actual award of the construction contract during which Avondale and Exxon engineers went through the design to identify to the maximum extent possible all major items of equipment and the system design of all systems which would be installed in the ship. The goal was to have a completely defined package decided upon prior to the award of the contract to build that package.
Although the design changes were important, the primary emphasis of this first effort at Avondale was directed at the production effort—at reducing production manhours. There are three major conceptual approaches which, in combination, have effected an entirely different approach to building ships at Avondale.
Production Line The first of these changed construction approaches might be called a "production line" shipconstruction technique. Instead of laying the keel on the shipbuilding ways and constructing the ship progressively from the keel up and from the middle of the ship toward each end, with the "production line" approach, sections of the ship are moved along from position to position in the shipyard.
At each position, certain types of work are accomplished. After work on a unit is completed at one position, the unit is moved to another position for additional types of work to be done.
This results in many units of the ship being constructed simultaneously in different parts of the shipyard. Only after each unit is complete is it moved to the shipbuilding ways for assembly into the ship itself. Of course, we do erect these units on the ways, from the keel up and from the machinery space forward and aft, but the pieces which we erect are whole units of the ship with as much piping and equipment already installed as it is economical to do.
The process begins with an analysis of the entire structure of the ship, breaking it down into units which are suitable for handling with the shipyard cranes and other facility capacities. Under the tutelage of our Japanese advisors, Avondale production personnel classified each portion of the hull into one of six different categories, depending on the complexity of each category to be built. The simplest category is one constructed of flat pieces of material welded together. Fortunately, more than half of the units of the ship are constructed of these relatively easy-to-build units.
At least part of the. art of breaking the ship up into units is to select as many units as possible which can be constructed using the techniques associated with the less complicated categories. Then, again under the guidance of IHI advisors, Avondale set aside certain areas of the shipyard where this type of construction would be carried out exclusively.
The result is that in the areas where this type of construction is accomplished, the workers accomplish exactly the same kind of work each day. As they complete one section, the ship section moves to the next work site, and another section is constructed at the first site by the same people using exactly the same techniques. This then leads to the description of this process as a "production-line shipbuilding technique." Outfitting The second major change in technique is the installation of piping, ventilation and other systems on each of these units as they are being constructed. Thus, after one unit of the hull reaches the appropriate level of construction, it will be moved to a location in the shipyard where the pipefitters and ventilation people and other system installers will take over and install their systems. This is called "outfitting" the unit.
Following outfitting, the section of hull may go to a different spot in the shipyard where another piece of plate will be added to cover up that area that has just been worked on. In this way, each system is installed at the point of construction where it is most easily installed. One essential point to note at this point of construction is that the design of the entire piping system in that portion of the ship must already have been completed.
Thus, by the time the entire unit is ready to be erected at the erection site, the majority of all the internal work has already been accomplished. All that remains to be done is to join the piping systems in one unit to the piping systems in another unit with short lengths of pipe called connecting pieces. The wireways for electrical installations will be installed during this period but the cables actually are run after the units have been assembled.
Packaging The third major difference in construction technique involves utilization of so-called "package units." The package unit is a combination of related equipment, such as pumps, controllers, gageboards, etc., constructed and installed on their foundations and all piped and wired. It is completed as a package with the entire system constructed and tested before installation.
Engineering Now, concerning the engineering efforts. This requires a considerably different effort on the part of the design and engineering personnel in order to effect these savings for production personnel.
The entire design must be virtually complete before production can efficiently start. For example, the first production effort related to most pieces of steel structure is to cut the piece out of a larger piece. That is also the most efficient point of construction to cut all of the holes which must be cut in that piece. However, in order to know where to cut all the holes, the detailed design and routing of every piece of piping, or ducting, or electrical cable which will finally pass through that piece of steel must be complete.
The result of these many changes was a considerably larger engineering effort on this first project, compared to the "conventional" technique. However, the payoff was in the many fewer hours spent in production correcting the interferences between the larger and the smaller sections of piping.
Another aspect of the design process is the need to identify all of the equipment which will be installed on the ship right at the very beginning of the design process.
In order to minimize the wastage of time it is mandatory that we know precisely what pumps, what engines, what gear, etc., will be installed in the ship as soon as possible after the design effort begins.
The results to date have been very satisfying to Avondale's management.
Avondale's production manhours have been significantly reduced compared to the manhours which would have been expected had the ships been built in the "conventional" manner. The reduction in production manhours have much more than offset the increase in engineering manhours in this first effort to apply the new shipbuilding technique.
Needless to say, Avondale is not alone. Most other shipyards in this country are adopting the majority of these concepts in their building process today. So we can definitely say that the productivity of U.S.
shipyards is improving.
Of course, production and engineering labor costs are not the whole cost story. Analyses of shipbuilding, whether in the U.S. or abroad, have demonstrated that approximately half of the cost of a commercial ship is in material.
Thus, even if we were to reduce manhours in half, we will still not be as competitive in the world market as we want to be until the material and equipment costs can be made competitive.
Read Productivity Advances In Shipbuilding in Pdf, Flash or Html5 edition of November 1983 Maritime Reporter
Other stories from November 1983 issue
Content
- Indonesia Signs $150-Million Agreement For 4 Boeing Jetfoils page: 5
- Joint Venture Formed By Union Carbide And MTL page: 5
- Marine Consultants To Conduct Study For MarAd On Bulk Carriers page: 6
- Glomar Robert F. Bauer Christened At FELS page: 6
- Global Marine Introduces New Designs For New Generation Of Heavy Weather Jackups page: 6
- McDermott Pla ns Study Of Fixed Platforms For 1,600-Foot Water Depths page: 7
- M i t c h e l l M a r i n e Delivers Fourth Service Boat page: 7
- North Sea Maureen Field Commences Oil Production page: 8
- Swift Group Management Promotions Announced page: 8
- Bay Shipbuilding Building Coal Topping Off Barge page: 8
- Radm. Nunneley New President Of ASNE page: 9
- Ship Survivability Topic Of Symposium In Philadelphia December 7 page: 10
- Miniliner Newport Clipper Delivered By Jeffboat page: 10
- Marinette Marine Awarded $6-Million Navy Contract page: 11
- ASNE Call For Papers For '84 Naval Ship Symposium page: 11
- Third ARS Keel Laying At Peterson Builders page: 12
- Navy Awards Tracor $7.7-Million Contract page: 12
- Thomas Marine Offers 38' Aluminum Crewboat —Literature Available page: 12
- Free Mobil Literature Details New Diesel Oil For High Output Engines page: 13
- Nav-Com Names Franza Director Of Marketing page: 13
- Nichols To Build New Seattle Fireboat page: 14
- Offshore Drilling Rig Sedco 602 Delivered By Promet Shipyard page: 14
- Uniroyal Fendering To Be Fitted On ARAMCO Tug —Literature Available page: 14
- Farrell Lines To Test U.S. Sea Shed System's Commercial Applications page: 15
- CSSRA 1984 Technical Conference Set For February 14 In Montreal page: 16
- McDermott To Build $6-Million Matson Container Barge page: 16
- Changes In The Navy Shipbuilding Program — An Update — page: 16
- New 8-Page Brochure On Micro = Lam Scaffold Planks Offered Free By Trus Joist page: 17
- New Updated Edition Of "American Harbour Pilot" By Hans Gade Is Available page: 18
- CRC Welding Systems Moves To Houston page: 18
- ACR Projects Business Improvement For 1984 page: 19
- Ogden Corporation Announces Spinoff Of Ogden Marine Inc. page: 19
- Rail Deregulation, User Taxes Threaten Barge And Towing Industry page: 20
- Icebreaker Contract For Halifax Shipyard Totals Can. $54 Million page: 21
- AMP Introduces New Line Of Ribbed Wire Splices —Literature Available page: 21
- Dock Express Changes Management Structure page: 24
- RMI Adds Four Members To Board Of Directors page: 25
- Wartsila Diesels To Power Sonat Semisubmersible —Literature Available page: 25
- The Marine Board Of The National Research Council Plans November Symposium page: 26
- Blount Marine Gets Orders For Three New Vessels page: 26
- PIMA Established As Shipbuilding/Repair Agents page: 26
- Navy Saves $22 Million In Three Months With Competitive Bidding Plan page: 27
- Butterworth Names Smith Tank Cleaning Machine Product Line Coordinator page: 27
- U.S. And Canadian Companies Licensed To Build Vickdock page: 27
- Rice Named Director of AMB Barge Train page: 29
- Halter-Built Paddlewheeler Is First Exhibit Completed For 1984 Louisiana World's Fair page: 30
- OFFSHORE RESURGENCE BEGINS page: 32
- N.Y. Port Engineers Society Discusses Importance Of Propeller Finish page: 33
- N e w M o n i t o r i n g System Can Reduce Fuel Costs — L i t e r a t u r e A v a i l a b le page: 34
- Halter Marine Completes Contract With Tidewater page: 34
- Great Lakes Towing Christens 250-Ton Drydock page: 35
- TCS Cuts Barge-Moving Costs With New Winch-Control System page: 36
- Financial Moratorium At Verolme Botlek Lifted page: 37
- Concrete Offshore Platform Designed By Foundation-Skanska page: 37
- Productivity Advances In Shipbuilding page: 38
- National Marine Names Mangan Service Manager page: 40
- Fetterolf Acquires Stacey Valve Products —Literature Available page: 40
- Mitsui Delivers The Kepbreeze page: 45
- SNAME Gulf Section Meets In Biloxi page: 45
- Armco Adds Forging Capability For Stainless-Steel Products —Free Literature Available page: 45
- Submarine Honolulu Launched At Newport News Shipbuilding page: 45
- The New Boston Shipyard Begins Operations page: 46
- A New Concept In Chemical Barge Transportation page: 47
- MARCO Pacific To Build New Design Tuna Purse Seiner page: 47
- Free 200-Page Book Describes The Corrosion Resistance Of Zinc page: 48
- $140-Million Contract To Daewoo Shipbuilding page: 48
- ASTM Standards Committee On Shipbuilding To Meet In Seattle In November page: 49
- Wartsila Opens Newest Factory In Singapore —Engine Literature Available page: 50
- 91st S N A ME Annual Meeting Second International Maritime Exposition page: 54
- Power Factor Savings W i th Energy Efficient M o t o rs page: 86
- B u r r a r d Y a r r o w s To B u i l d T w o I c e b r e a k e rs For Can. $ 1 0 8 . 5 - M i l l i on page: 86
- M o r m a c Ship Saves Fuel W i t h Westinghouse C o n t r o l System — L i t e r a t u r e A v a i l a b le page: 88
- Maritime Satellites Now Reach 2,000 Users page: 89
- Electro-Nav Brochure Describes Microprocessor Controlled Marine Receiver page: 89
- Innovative "Flexor" Barge Connector Allows Blue Water Barge Trains page: 90
- Bay Shipbuilding Converts Ex-President Harrison page: 90
- Caterpillar Offers Free Literature On New Lift Truck For Containers page: 92
- Squire-Cogswell Offers Literature On Oil-Free Marine Air Compressors page: 92
- $250,000 Order For Atlas Fishing Systems —Literature Available page: 95
- Fire-Tested Valves And Actuators Described In Free Jamesbury Brochure page: 97
- Port Allen Marine Offers Four-Color Brochure On Full Shipyard Services page: 98
- Free 4-Color Howe Baker Brochure Shows How New Burner Cuts Fuel Costs page: 100
- Magnus Maritec Completes $2 Million Expansion Of Fuel Oil Testing Service —Literature Available page: 101
- Navy Lets $8.3-Million Contract To Tracor page: 102
- Moss Point Building Five Other Vessels For Joint Venture page: 104
- Hoffman Maritime Names Finn C. Michelsen Technical Director page: 106
- Economic Benefit Of FY 84 Navy Construction Program Outlined By Shipbuilders Council page: 108
- Northern New England ASNE Announces 83-84 Program page: 109
- GM Increases Diesel Power Ratings And Offers New Applications Manual page: 110
- N e w L i t e r a t u r e Describes T h o r d o n Shaft Bearings For D i r t y W a t e r O p e r a t i on page: 111
- Maritime Prepositioning Conversions Begin At Bethlehem's Beaumont Yard page: 112
- Split-Hull Hopper Dredge Delivered By Nichols page: 117
- SNAME Metropolitan Section Reviews T-AKX Ship Conversion page: 118
- Halter Marine Completes Four-Boat Contract For Zapata Marine page: 118
- Captain Grabb Appointed ASNE Technical Director page: 120
- Free Literature Available On Marconi's New ARPA page: 122
- Cousteau Begins River D o c u m e n t a r y ; Biehl And Company Named Agent page: 129