February 1977 - Maritime Reporter and Engineering News

Dravo Corp. Awarded $4 Million To Build Barge Unloader

Dravo Corporation, Pittsburgh, Pa., has received a contract in excess of $4 million to design, engineer and build a continuous bucket-elevator barge unloader for Cajun Electric Power Cooperative, Inc. of New Roads, La.

The new unloader, designed to unload 5,000 tons of coal an hour from jumbo barges in a two-pass operation, will be installed at the utility's new Big Cajun #2 Power Station on the Mississippi River near Baton Rouge. The operation will also include a Dravo-patented shuttle barge hauling system.

Coal will be shipped from Wyoming and Montana by rail to a coal terminal in St. Louis, Mo., and sent by barge to the power station. Approximately four million tons a year of lowsulfur coal will be used to generate electricity in Cajun Electric Power's two 540-megawatt generating units.

Dravo, with more than 50 years' experience in designing and constructing handling systems, is one of the world's leading manufacturers of bulk materials handling equipment.

Other stories from February 1977 issue

Content

Maritime Reporter

First published in 1881 Maritime Reporter is the world's largest audited circulation publication serving the global maritime industry.